Construction of Asphalt Road from Rahab to Khabut Village at Marmul for WGCCC/PDO


This is a fast track project wherein the project duration is of 04 months. Total length of the project is 13 Kms with various provision of Cross Drainage works like 16 no’s Pipe culverts of various cells and 7 no’s Irish Crossings of a total length of 930 mts. This project is located in the PDO South Oman interior and has a high risk because of the close proximity of Oil & Gas pipelines locations and Live Electrical crossings. Mobilization period and the design period are of a shorter duration in which resources were arranged at a short notice. Due to the geographic location of the project and its distance from Capital area, this project required lot of attention to planning / procurement / scheduling of transportation of project construction materials